ANDRA has rejected any chance of leasing Sydney's Eastern Creek Raceway
to stage the 1998 Premier State Nationals, under the sort of conditions
suggested by the Australian Racing Drivers Club (ARDC).
ANDRA had proposed the leasing of the Sydney track in a submission written
to ARDC General Manager Chris Hones on June 2. The idea was to lease the
track for a period of a week, from mid-week to mid-week, preferably in
October, during which a street meet would be staged, then the championship
season-launching Premier State Nationals, after which the surface would not
be cleaned of its traction compounds, to fulfill the track's CAMS
(Confederation of Australian Motor Sports) circuit racing licence, but would
have a fresh coat of asphalt applied from the end of the concrete to just
past the quarter mile finish line.
The four-page reply to ANDRA's submission did not set out any specific
costs, but made a number of broad suggestions related to the cost of running
such an event. The letter suggests a loss of alternate hiring fees (to Grand
Prix bike team testing) of $10,000 per day, which for the seven-day suggested
hire period, plus a further 21 days during which the track "would be out of
action," making a total of $280,000 for the hire, payable to the ADRC.
Willowbank manager and NCC member Dennis Syrmis told DRAGSTER that he
could not understand why there would need to be a period of 21 days break in
the track's availability.
"When we built Willowbank we waited until the last possible moment before
laying the final coat of asphalt so that we earned income from it as soon as
possible after it was down ", said Syrmis, "and it went down four days before
the first pass was made on the track. Generally it's recommended that five
to six days after it's laid be allowed, but you can safely get away with
four days.
We've done it whenever we've had to reseal sections of the track. I mean,
they resurface highways and you can drive on it within hours." When we
suggested that was not a reasonable analogy, since you don't run 5000
horsepower dragsters over highways, Syrmis retorted, "Yes, but you don't run
30-tonne semi-trailers over drag strips."
The ARDC letter suggested that the resurfacing would have to be to a
standard required by Grand Prix motorcycle and V8 touring cars, and would
cost an estimated $300,000. On this topic Syrmis and other sources suggested
to DRAGSTER that a reasonable figure for this, over the relatively short
distance required, would be closer to $40,000.
The ARDC's response that the $200,000 spent on staging the 1997 Premier
State Nationals had been highly criticised because of a lack of promotion,
therefore a minimum figure for the actual staging of the event would be
around $300,000, resulting in a "total event cost to ANDRA of $880,000."
The letter went on to reiterate the ARDC's position in regard to building
a separate drag strip on the site, against which the ARDC, it claimed had
paid out close to $10,000 in planning costs. "We have not yet called on
ANDRA to assist with these escalating and continuing costs," the letter
states.
The letter suggests "ANDRA should be making formal approaches at State
and Federal Government levels for funding." Investigations by DRAGSTER with
the NSW (New South Wales) Department of Sport and Recreation indicate that
the lease for the Eastern Creek property quite specifically prohibits the
expenditure of any NSW government funds, either by grant or loan, on any
activity at Eastern Creek, either through the ARDC or any associated
organization or sub-lessee. This condition was stated in pre-lease conditions
when submissions were called for, and has since been conveyed to ARDC
officials on a number of occasions.
The letter continues, "Lobbying for one big event to solve everything is
not the long term solution," then states that if a separate drag strip is
built at the track ANDRA could do what AVESCO/SEL do with the V8 touring
cars, hiring the facility for a share of the gate and entry fees payable to
the ARDC and paying all expenses, such as cleaning, toilets, security,
printing, etc., so that "ANDRA could get an income direct from major events,
say two or three each year."
ANDRA's response was to reject such a proposal, and that the suggested
figure of around $880,000 was "unrealistic", and that plainly the ARDC
"places a low priority on drag racing at anything above the off-street level
at the moment."
The ARDC's approach, which is one of minimal spending, showed at a recent
street meet where a street car oildown resulted in the track being cut back
to single lane use only because of a lack of materials to clean it up.